Dashboard: New Template "Project Health"

With the new "Project Health" dashboard template, you can keep track of the overall status of your projects at all times – compact, visual, and insightful. The dashboard displays the status from three key perspectives:

  • Time: Based on the time alerts "Planned end date exceeded" and "Project end date exceeded"
  • Budget: Compares planned vs. actual values. Using the dashboard parameter settings (button at the very top right), you can customize the percentage range for budget alerts
  • Risk: Evaluated according to the level of risk (set on the project manage page)

From these, an overall status is calculated as the average of the three values Time, Budget, and Risk.

You can download this and other templates under Templates and then import them into InLoox.

Dashboard "Project Health": Overall project status based on time, budget, and risk